Follow the phases of the project
- Discovery: goals, sitemap and content plan.
- Design: the home page and the key templates.
- Build: development, content and testing.
- Launch: the site goes live.
Each phase ends with a deliverable and an approval. Those approvals are your milestones.
Three schedules that work
Example: a four-stage $12,000 website
- DepositAt kickoff$3,000.0025%
- Design approvedWhen “Design approved” is approved$3,000.0025%
- Site ready for reviewWhen “Site ready for review” is approved$3,000.0025%
- LaunchWhen “Launch” is approved$3,000.0025%
Make approvals happen
A milestone payment waits for an approval. Write down what approval means, and how long the client has to give it.
- Send each deliverable with a date: “please approve or send feedback by 12 March”.
- Agree what happens without an answer, for example: approved after 10 business days.
- Keep extra rounds of changes out of the milestone. Price them as a change order.
Do not leave most of the money for the launch
Launches slip, often while the site waits for the client's content. If most of the money is due at launch, your pay slips with it. Keep the launch payment at a third of the total or less, or add a date: “at launch, or 30 days after the build is approved, whichever comes first”.